Concrete volume
A quantity take-off for a single element. Not a mix design, programme or pour sequence.
Method
Rectangle: L × W × t, with thickness converted from millimetres. Cylinder: πd²h/4. Allowance is a multiplier, not measured wastage.
Worked slab: 4.5 × 2 × 0.200 = 1.800 m³ net, 1.890 m³ at 5%.
Logic: how this figure is built.
Last checked 2 October 2026. Worked figures are scenarios. See methodology and the disclaimer.